Here is the weekly press release for the Thacker Pass project, for the week ending in February 14, 2025.

Sculpted from Thacker Pass’ rugged terrain, this aerial closeup reveals the precise earthwork engineering at our process plant pad. The carefully graded surfaces and defined edges showcase the meticulous site preparation, laying the literal groundwork for North America’s largest lithium project. 

Thacker Pass updates:

Sawtooth Mining, our mining partner/contractor who is performing most of the construction-related earthwork is continuing excavation of the process plant pad, which is 90% complete.  

Highmark Construction, our general fill earthworks contractor, is nearly 90% complete with general fill placement.

Pictured above is the temporary batch plant which is in operation. 

Malta Ready Mix, our concrete foundation contractor, is installing their concrete batch plant on site. As of this week they have placed approximately 450 cubic yards (CY) for their temporary facilities. The first large concrete pour for the process plant area is scheduled for May 2025.

pictured above, is in initial operations. Testing will follow to ensure quality meets engineering requirements. 

Ames Construction select fill processing plant, pictured above, is in initial operations. Testing will follow to ensure quality meets engineering requirements. 

The fill plant involves a collective of heavy machinery that transforms raw rock into optimal foundation material that meets project requirements to support a stable foundation for the plant facilities. 

The final step will be sending it through a cone crusher that works in harmony with a secondary screen. The result will be precisely sized structural fill that will provide the stable foundation needed for Thacker Pass’s future processing facilities.  

Thacker Pass continues to be in regular communication with state and federal agencies regarding construction progress, and safety and environmental compliance.

Companies currently on site at Thacker Pass: 

 

Company:  Role:  
Lithium Americas Corp Primary owner of the Thacker Pass Project 
Sawtooth MiningMining contractor performing most of the construction-related earthwork  
Bechtel   Engineering, procurement and construction management (EPCM) contractor
Gamma Electric    Electrical contractor  
Allied Universal Security     Site security
Hunt & Sons    Fuel supply
Desert Disposal   Waste management 
GrayMar Environmental, Inc.    Environmental field services

Ruby Mountain Natural Spring Water  
Drinking water supplier 
Empire CAT   Heavy equipment supplier and servicer  
Komatsu   Equipment supplier and servicer  
NewFields       Civil engineering: design, geotechnical analysis, quality assurance
Black Eagle  Geotechnical analysis to include soil and concrete testing to ensure quality work is performed. 
  High Mark Construction    General fill earthworks contractor  
Malta Ready Mix   Concrete foundation contractor  
Ames Construction Select/structural fill processing 
Stoney Basin  Road maintenance 
Hunewill Construction     Aggregate supplier
Sanbell Engineering     Land surveying 
Piteau Associates  
Water monitoring  
Diversified Transportation Employee transportation bus service, connecting Winnemucca to Thacker Pass 

Workforce Hub updates: 

Construction milestones are stacking up at our Workforce Hub where over 380 pre-cast foundations are pictured dotting the landscape. As Joy Engineering shapes the terrain with precision grading and structural fill, concrete work approaches 30% completion. These foundations are the building blocks of our future housing facility where the on-site team building Thacker Pass will rest and recharge. 

City of Winnemucca building inspections are ongoing.  Sanbell Engineering, our civil engineering contractor, is inspecting concrete placement for foundations of the modules, as well as off-site water and sewer installations.  Target Hospitality, the contractor selected for installation and operation of the Workforce Hub, is conducting pre-installation inspections on modules and assisting with final engineering to prepare for setting the modules in place.   

Offsite utility construction activities are ongoing at Rim Rock Road. There will be partial road closures in this area for a few weeks as Hunewill completes road work.  Progress on the foundation includes the following:   Joy Engineering, our contractor for sewer, drainage and roadways is currently grading and generating structural fill.   More than 380 pre-cast foundations have been set.  Concrete placement is nearly 30% complete. 

Companies currently on site at the Workforce Hub:  

Company:  Role:  
Lithium Americas Corp Owner of the Workforce Hub 
Bechtel Engineering, procurement and construction management (EPCM) contractor 
Wood Group  Structural engineer 
Sanbell Engineering  Civil engineer 
Joy Engineering Installing onsite sewer improvements and roadways   
Brahma Group Concrete foundation contractor 
Jensen Pre-Cast Concrete foundation contractor 
Nevada Building Supply (NBS) Aggregate supplier, also supplying structural steel  
Humboldt Ready Mix Concrete foundation contractor 
Ruby Mountain Natural Spring Water  Drinking water supplier 
Desert Disposal   Waste management 
Civeo  Vendor of the Workforce Hub modules
Karve Builders Civeo’s contractor on site for module remediation 
ServiceMaster   Assisting Karve with preparing the modules 
Target Hospitality Contractor selected for installation and operation of the Workforce Hub 

Message from Lithium Americas: “We hope you enjoy our Thacker Pass Weekly Updates, as we are committed to providing information on the progress we’re making at Thacker Pass.”