Thacker Pass updates:

Sawtooth Mining, our mining partner/contractor who is performing most of the construction-related earthwork is continuing excavation of the process plant pad, which is over 90% complete.  


Highmark Construction, our general fill earthworks contractor, is over 90% complete with general fill placement. 

Malta Ready Mix, our concrete foundation contractor, is installing their concrete batch plant on site. As of this week, they have placed approximately 450 cubic yards (CY) for their temporary facilities. The first large concrete pour for the process plant area is scheduled for May 2025. Pictured above is the temporary batch plant which is in operation. 

Ames Construction select fill processing plant, pictured above at site on Feb. 13, 2025 is in initial operations. Testing will follow to ensure quality meets engineering requirements. 

The fill plant involves a collective of heavy machinery that transforms raw rock into optimal foundation material that meets project requirements to support a stable foundation for the plant facilities. 

Pictured above, the crushed rock travels up conveyors to a three-deck screening system that sorts the material like a geological gold panner. The final step will be sending it through a cone crusher that works in harmony with a secondary screen. The result will be precisely sized structural fill that will provide the stable foundation needed for Thacker Pass’s future processing facilities.  

Thacker Pass continues to be in regular communication with state and federal agencies regarding construction progress, and safety and environmental compliance.   

Companies currently on site at Thacker Pass: 

Company:  Role:  
Lithium Americas Corp Primary owner of the Thacker Pass Project 
Sawtooth MiningMining contractor performing most of the construction-related earthwork  
Bechtel   Engineering, procurement and construction management (EPCM) contractor
Gamma Electric    Electrical contractor  
Allied Universal Security     Site security
Hunt & Sons    Fuel supply
Desert Disposal   Waste management 
GrayMar Environmental, Inc.    Environmental field services

Ruby Mountain Natural Spring Water  
Drinking water supplier 
Empire CAT   Heavy equipment supplier and servicer  
Komatsu   Equipment supplier and servicer  
NewFields       Civil engineering: design, geotechnical analysis, quality assurance
Black Eagle  Geotechnical analysis to include soil and concrete testing to ensure quality work is performed. 
  High Mark Construction    General fill earthworks contractor  
Malta Ready Mix   Concrete foundation contractor  
Ames Construction Select/structural fill processing 
Stoney Basin  Road maintenance 
Hunewill Construction     Aggregate supplier
Sanbell Engineering     Land surveying 
Piteau Associates  
Water monitoring  
Diversified Transportation Employee transportation bus service, connecting Winnemucca to Thacker Pass 
Pictured above: an aerial view of the Lithium Americas Workforce Hub blanketed in a northern Nevada February snow. Despite the winter covering, the deliberate contours of precision grading remain visible, showcasing recent earthwork progress. Joy Engineering continues terrain development with structural fill placement, while concrete placement has reached nearly 30% completion. 

Workforce Hub updates: 

City of Winnemucca building inspections are ongoing.  Sanbell Engineering, our civil engineering contractor, is inspecting concrete placement for foundations of the modules, as well as off-site water and sewer installations.  Target Hospitality, the contractor selected for installation and operation of the Workforce Hub, is conducting pre-installation inspections on modules and assisting with final engineering to prepare for setting the modules in place.  

This week, Target Hospitality announced their multi-year Workforce Hub contract advancing strategic diversification and regional network expansion. Read their announcement on PR Newswire, and Benzinga.   Offsite utility construction activities are ongoing at Rim Rock Road.

There will be partial road closures in this area for a few weeks as Hunewill completes road work.  Progress on the foundation includes the following:   Joy Engineering, our contractor for sewer, drainage and roadways is currently grading and generating structural fill. More than 380 pre-cast foundations have been set. Placement of pre-cast foundations is nearly 30% complete. 

Companies currently on site at the Workforce Hub:  

Company:  Role:  
Lithium Americas Corp Primary owner of the Thacker Pass Project 
Sawtooth MiningMining contractor performing most of the construction-related earthwork  
Bechtel   Engineering, procurement and construction management (EPCM) contractor
Gamma Electric    Electrical contractor  
Allied Universal Security     Site security
Hunt & Sons    Fuel supply
Desert Disposal   Waste management 
GrayMar Environmental, Inc.    Environmental field services

Ruby Mountain Natural Spring Water  
Drinking water supplier 
Empire CAT   Heavy equipment supplier and servicer  
Komatsu   Equipment supplier and servicer  
NewFields       Civil engineering: design, geotechnical analysis, quality assurance
Black Eagle  Geotechnical analysis to include soil and concrete testing to ensure quality work is performed. 
  High Mark Construction    General fill earthworks contractor  
Malta Ready Mix   Concrete foundation contractor  
Ames Construction Select/structural fill processing 
Stoney Basin  Road maintenance 
Hunewill Construction     Aggregate supplier
Sanbell Engineering     Land surveying 
Piteau Associates  
Water monitoring  
Diversified Transportation Employee transportation bus service, connecting Winnemucca to Thacker Pass 