Thacker Pass updates:

Excavation of the process plant pad is ongoing and is over 80% complete. 

Road construction is progressing on site. In December, rumble tracks were installed at the site entrance/exit that connects with NV-293. The rumble tracks help reduce debris from vehicles leaving site, especially on muddy days, reduce the need for water trucks and street sweeping, and with dust abatement as well as soil stabilization. 

We also hired Stoney Basin to help us manage track out from vehicle debris on HWY293. 

High Mark Construction is more than 50% complete with the general fill for the process plant pad. The updated photo above shows progress for site road construction where High Mark placed culverts to manage runoff.   

Companies currently on site at Thacker Pass: 

Company: Role: 
Lithium Americas Corp Primary owner of the Thacker Pass Project
Sawtooth Mining Mining contractor performing most of the construction-related earthwork
Bechtel  Engineering, procurement and construction management (EPCM) contractor 
Gamma Electric  Electrical contractor  
Allied Universal Security  Site security 
Hunt & Sons  Fuel supply 
Desert Disposal Waste management 
GrayMar Environmental, Inc.  Environmental field services 
Ruby Mountain Natural Spring Water Drinking water supplier 
Empire CAT Heavy equipment supplier and servicer 
Komatsu  Equipment supplier and servicer 
NewFields  Civil engineering: design, geotechnical analysis, quality assurance 
High Mark Construction  General fill earthworks contractor 
Malta Ready Mix Concrete foundation contractor 
Stoney Basin Road maintenance 
Hunewill Construction Aggregate supplier 
Sanbell Engineering Land surveying 
Piteau Associates Water monitoring 
Workforce Hub updates:  Permits for installation of utilities such as water, sewer, and fiberoptic cable are being finalized  Joy Engineering is installing onsite sewer improvements and generating structural fill for foundation placement Contracts were recently awarded to:   Humboldt Ready Mix, Jensen Pre-Cast, and Brahma Group for building concrete foundations  Hunewill Construction for offsite utility installation  Target Hospitality for the overall facility installation and operation 

Companies currently on site at the Workforce Hub:  

Company:  Role:  
Lithium Americas Corp Owner of the Workforce Hub 
Bechtel Engineering, procurement and construction management (EPCM) contractor 
Wood Group  Structural engineer 
Sanbell Engineering  Civil engineer 
Joy Engineering Installing onsite sewer improvements and roadways   
Brahma Group Concrete foundation contractor 
Jensen Pre-Cast Concrete foundation contractor 
Nevada Building Supply (NBS) Aggregate supplier, also supplying structural steel  
Humboldt Ready Mix Concrete foundation contractor 
Ruby Mountain Natural Spring Water  Drinking water supplier 
Desert Disposal   Waste management 
Civeo  Vendor of the Workforce Hub modules
Karve Builders Civeo’s contractor on site for module remediation 
ServiceMaster   Assisting Karve with preparing the modules 
Target Hospitality Contractor selected for installation and operation of the Workforce Hub 

Journey to the Origins of the McDermitt Caldera 

This week we shared a captivating dive beneath earth’s surface in our latest animation. Our new video brings the remarkable geology of North America’s largest lithium deposit to life by illustrating how the caldera was formed, and what makes the lithium-bearing volcanic clay at Thacker Pass unique.  Journey beneath the surface via our YouTube channel!

The size and multigenerational expansion potential of Thacker Pass was supported by the release of our NI 43-101 and S-K 1300 Technical Reports last week. The updated lithium mineral reserve and resource update is a significant milestone in our company’s journey. Thacker Pass is now the largest known measured lithium resource in the world.)

Categories:

Tags:

No responses yet

Leave a Reply

Your email address will not be published. Required fields are marked *